Which of the following best describes a 'square foot cost' method using published cost data?
-
A
An order-of-magnitude estimate based on cost per square foot of a building type
-
B
A detailed line-item estimate for every material and labor operation
-
C
A bid submitted by a subcontractor based on drawings
-
D
A cost-plus contract pricing method