How does 'fast-tracking' affect project cost estimates?
-
A
Always reduces total project cost
-
B
Overlaps design and construction phases, potentially increasing cost through rework and coordination
-
C
Eliminates all contingency needs
-
D
Has no cost impact — it only affects schedule