What does the term 'net present value' (NPV) mean in engineering economics?
-
A
The current worth of all future cash flows discounted at a required rate of return
-
B
The total undiscounted profits from a project over its lifetime
-
C
The ratio of benefits to costs at current prices
-
D
The book value of assets after depreciation