Which PROFIBUS DP baud rate requires the use of cable Type A to achieve the full specified segment length?
Answer: 12 Mbit/s
At 12 Mbit/s, only Type A cable (shielded, 135–165 Ω, low capacitance) can reliably cover the specified 100 m maximum segment length.
When connecting a PROFIBUS PA device to a DP/PA coupler, what is the typical trunk line impedance used?
Answer: 100 Ω (IEC 61158-2 Type A)
PROFIBUS PA uses IEC 61158-2 Type A cable with 100 Ω balanced impedance for the trunk and spur connections.
What is the recommended action when a PROFIBUS repeater is added to extend a segment beyond the maximum node count?
Answer: Terminate each segment independently at both ends
Each segment separated by a repeater must be independently terminated at both physical ends to prevent signal reflections.
During PROFIBUS installation, what does a 'Retry_Error' counter incrementing on the master indicate?
Answer: The master is retransmitting requests due to no or corrupt responses
An incrementing Retry_Error counter means the master is not receiving valid responses and is retransmitting, indicating communication failures on the bus.
What is the effect of setting a slave's watchdog timeout too short during commissioning?
Answer: The slave frequently enters safe state unnecessarily during normal communication delays
A watchdog timeout set shorter than the maximum master cycle time will cause the slave to enter safe state during normal operation, triggering unnecessary safety shutdowns.
When a PROFIBUS GSD file specifies 'Freeze_Mode_supp = 1', what commissioning capability does this enable?
Answer: Synchronizing input data capture across multiple slaves simultaneously
Freeze_Mode allows the master to issue a global freeze command, causing multiple slaves to simultaneously latch their input data for synchronized acquisition.
Which physical layer test is performed first when troubleshooting a PROFIBUS segment that shows intermittent communication failures?
Answer: Termination voltage measurement
Measuring termination voltage (typically 3.7–5.0 V between A and B lines with no traffic) quickly confirms whether bus termination is correctly applied.