  1. When a vendor offers an early payment discount of '2/10 net 30', this means:

    Answer: A 2% discount is available if paid within 10 days; otherwise, full payment is due in 30 days

    2/10 net 30 is a standard trade credit term meaning a 2% discount is earned by paying within 10 days, with the full invoice due in 30 days.

  2. A general contractor using a 'sole-source' subcontractor strategy for a specialty trade is accepting which primary risk?

    Answer: Limited price competition, potentially inflating subcontract cost

    Without competitive bidding, sole-source procurement removes market pricing pressure, which may result in paying above-market rates for the specialty work.

  3. A subcontractor's lien waiver upon final payment is important because it:

    Answer: Releases the property from any claim the subcontractor could file for unpaid work

    A final lien waiver is a legal release confirming the subcontractor has been paid in full and forfeits the right to file a mechanic's lien against the property.

  4. During bid day, a subcontractor calls to withdraw their bid after the GC has submitted the prime bid relying on it. This situation is related to the legal doctrine of:

    Answer: Promissory estoppel

    Promissory estoppel may prevent a subcontractor from revoking a bid when the GC reasonably relied on it in submitting their prime bid.

  5. Which subcontractor selection criterion is most relevant when evaluating safety performance?

    Answer: Experience Modification Rate (EMR)

    The Experience Modification Rate (EMR) quantifies a subcontractor's historical workers' compensation claims relative to industry average, directly measuring safety performance.

  6. A subcontract that includes a 'no damage for delay' clause means the subcontractor can only recover:

    Answer: A time extension for excusable delays but no additional compensation for delay costs

    A no-damage-for-delay clause limits the subcontractor's remedy for delay to a time extension only, barring monetary recovery for delay-related costs.

  7. When comparing vendor quotes for the same material, the estimator should verify that quotes include identical:

    Answer: Delivery terms, freight costs, and applicable taxes

    Delivery terms, freight charges, and taxes materially affect total material cost and must be consistent across all vendor quotes for a valid price comparison.