โ† All CPE Flashcard Decks

Subcontractor & Vendor Management Flashcards

7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Subcontractor & Vendor Management flashcards as text
  1. A subcontractor's certificate of insurance does not list the general contractor as an additional insured. The estimator should:

    Answer: Require the subcontractor to update the certificate before award

    The GC must be named as additional insured to receive direct protection under the subcontractor's policy in the event of a claim.

  2. Flow-down clauses in a subcontract are designed to:

    Answer: Transfer applicable prime contract obligations from the GC to the subcontractor

    Flow-down clauses ensure subcontractors are bound by the same terms in the prime contract that are relevant to their work scope.

  3. When soliciting bids from vendors, the estimator should include:

    Answer: Detailed specifications, quantity take-offs, and required delivery schedule

    A complete vendor solicitation package with specifications, quantities, and schedule enables accurate and comparable vendor quotations.

  4. A subcontractor includes a 'bid clarification' that excludes sales tax. The estimator should:

    Answer: Add applicable sales tax to the subcontractor's price in the estimate

    Sales tax is a legitimate project cost; if excluded from a bid, the estimator must add it to ensure the total estimate is complete.

  5. Which subcontractor management practice best reduces the risk of back-charges during construction?

    Answer: Clearly defining scope boundaries and interfaces in the subcontract

    Well-defined scope boundaries minimize disputes over who is responsible for work at the interface between subcontractors, reducing back-charge potential.

  6. A 'pay-if-paid' clause in a subcontract means:

    Answer: The subcontractor is only paid after the GC receives payment from the owner

    A pay-if-paid clause makes the GC's receipt of payment from the owner a condition precedent to the GC's obligation to pay the subcontractor.

  7. When tracking subcontractor costs against the estimate, the estimator uses which tool to monitor variance?

    Answer: Cost-to-complete analysis with a cost code breakdown

    A cost-to-complete analysis broken down by cost code allows the estimator to compare actual subcontractor spending against the original budget by work category.