Overhead & Profit Calculation Flashcards
7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Overhead & Profit Calculation flashcards as text
A contractor bids $500,000 and wins the job. If actual costs run $480,000 and overhead was budgeted at 10% of direct costs ($436,364 base), what is the actual profit in dollars?
Answer: $20,000
Actual profit = bid price minus actual total costs: $500,000 − $480,000 = $20,000.
Which term describes the practice of allocating a portion of home-office overhead to each project based on its share of total revenue?
Answer: Revenue-based proration
Revenue-based proration assigns home-office overhead to projects proportionally by each project's share of total company revenue.
A subcontractor markup of 10% is applied to cover the general contractor's overhead and profit on subcontracted work. This practice is known as:
Answer: Pass-through markup
A pass-through markup is the percentage a GC adds to subcontractor costs to cover its own overhead and profit on that work.
If a contractor's overhead rate is 18% of direct costs and direct costs for a project are $750,000, what dollar amount is allocated to overhead?
Answer: $135,000
$750,000 × 0.18 = $135,000 allocated to overhead.
Which method of recovering overhead is most appropriate when projects vary widely in labor intensity but have similar material costs?
Answer: Percentage of direct labor costs
Applying overhead as a percentage of direct labor captures variation in labor-intensive overhead drivers when labor intensity differs across projects.
A contractor earns $2,000,000 in revenue and spends $1,600,000 on direct costs and $300,000 on overhead. What is the net profit margin?
Answer: 10%
Net profit = $2,000,000 − $1,600,000 − $300,000 = $100,000; margin = $100,000 / $2,000,000 = 5%.
Extended general conditions costs that arise from an owner-caused delay are typically classified as:
Answer: Compensable job overhead subject to a change order
Extended general conditions caused by the owner are compensable and should be claimed via change order as additional job overhead.