  1. An elevation drawing shows a 'finished floor elevation' (FFE) of +2'-6" and the adjacent grade is 0'-0". What does this tell the estimator?

    Answer: The finished floor is 2 feet 6 inches above the reference grade

    FFE indicates the elevation of the finished floor surface relative to a benchmark or established datum, here 2'-6" above grade, affecting foundation and slab costs.

  2. What is the purpose of a 'keynote' system on construction drawings?

    Answer: To reference materials or conditions to a legend rather than cluttering the drawing with text

    Keynotes use numbered symbols that reference a legend or schedule, keeping drawing areas clean while still communicating material and installation requirements.

  3. A roof plan shows hatching in a triangular area adjacent to a valley. What does this hatching likely indicate?

    Answer: Special flashing or waterproofing at the valley intersection

    Hatching near roof valleys typically indicates special flashing, underlayment, or waterproofing treatment required at the intersection of two sloping roof planes.

  4. On a plumbing plan, a circle with a cross inside it (⊕) typically represents:

    Answer: A floor drain

    A circle with a cross is the standard symbol for a floor drain on plumbing drawings, indicating a drain set flush with the finished floor surface.

  5. When an architectural drawing shows 'N.T.S.' as the scale, what must an estimator do?

    Answer: Never scale the drawing — use only the written dimensions

    'N.T.S.' (Not To Scale) means the drawing cannot be measured for dimensions; the estimator must rely exclusively on written dimensions shown on the drawing.

  6. A detail drawing is referenced on a floor plan with the symbol '3/A-5'. What does this reference tell you?

    Answer: Detail number 3 is found on drawing sheet A-5

    The standard drawing reference format places the detail number above the line and the sheet number below, meaning detail 3 is located on sheet A-5.

  7. What does a 'phantom line' (long dash, two short dashes repeated) typically indicate on construction drawings?

    Answer: Alternate positions, repeated features, or items not part of the contract

    Phantom lines show alternate positions of moving parts, repeated details, or items adjacent to but not included in the scope of work.