Engineering Economics & Contract Management Flashcards
7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Engineering Economics & Contract Management flashcards as text
A project has a Benefit-Cost Ratio (BCR) of 0.85. What does this indicate?
Answer: The project returns $0.85 for every $1 invested
A BCR less than 1.0 means the present value of benefits is less than costs, indicating the project is not economically justified.
Under a Cost-Plus-Incentive-Fee (CPIF) contract, the fee increases when:
Answer: The contractor underruns the target cost
In a CPIF contract, the contractor earns a higher fee when actual costs fall below the target cost, sharing the savings with the owner.
What is the Modified Internal Rate of Return (MIRR) designed to address?
Answer: Multiple sign changes in cash flows causing multiple IRR values
MIRR resolves the problem of multiple IRR values that arise when a project's cash flow stream changes sign more than once.
In contract law, 'liquidated damages' clauses must be:
Answer: A genuine pre-estimate of loss, not a penalty
Liquidated damages must represent a reasonable estimate of the owner's actual loss at the time of contract formation to be enforceable.
A machine costs $50,000 and has a salvage value of $5,000 after 9 years. Using straight-line depreciation, the annual depreciation charge is:
Answer: $5,000
Annual depreciation = ($50,000 - $5,000) / 9 = $45,000 / 9 = $5,000 per year.
Which contract type places the MOST financial risk on the owner?
Answer: Cost-plus-percentage-of-cost
Cost-plus-percentage-of-cost contracts give the contractor no incentive to control costs since their fee grows as costs increase, maximizing owner risk.
The capitalized cost of a project with an annual operating cost of $20,000 and an interest rate of 5% is:
Answer: $400,000
Capitalized cost for a perpetual series = Annual Cost / Interest Rate = $20,000 / 0.05 = $400,000.