โ† All CPE Flashcard Decks

Cost Estimation & Budget Control Flashcards

7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Cost Estimation & Budget Control flashcards as text
  1. An S-curve in project cost management is used to represent:

    Answer: Cumulative planned and actual costs over time

    An S-curve plots cumulative planned value, earned value, and actual cost over time, showing typical slow-start, rapid-mid, and tapering-end cost patterns.

  2. Which technique involves identifying and quantifying the uncertainties in cost estimates using probability distributions?

    Answer: Monte Carlo simulation

    Monte Carlo simulation runs thousands of iterations using probability distributions for each cost element to produce a range of possible total costs.

  3. A contractor is awarded a Cost-Plus-Incentive-Fee (CPIF) contract. The fee increases when:

    Answer: Actual costs are lower than the target cost

    In CPIF contracts, the contractor earns a higher fee when actual costs come in below the target cost, incentivizing cost efficiency.

  4. Variance at Completion (VAC) is calculated as:

    Answer: BAC - EAC

    VAC = BAC - EAC, representing the expected final cost variance (positive = under budget, negative = over budget) at project completion.

  5. Which element of the Work Breakdown Structure (WBS) is typically the lowest level used for cost estimation?

    Answer: Work package

    Work packages are the lowest WBS level where costs can be reliably estimated, scheduled, and tracked.

  6. A project cost estimate that accounts for price escalation over a multi-year project is called:

    Answer: An escalated or inflated estimate

    An escalated estimate adjusts future-year costs for expected inflation or price increases over the project duration.

  7. When should a project manager formally request a change to the cost baseline?

    Answer: When an approved scope change impacts the project budget

    Cost baseline changes require an approved scope change through the integrated change control process; cost overruns alone do not justify re-baselining.