Cost Estimation & Budget Control Flashcards

7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Cost Estimation & Budget Control flashcards as text
  1. Which estimating method is most accurate but also the most time-consuming?

    Answer: Bottom-up estimating

    Bottom-up estimating requires detailed estimation of each work package, making it the most accurate and most labor-intensive method.

  2. In earned value management, what does the Budget at Completion (BAC) represent?

    Answer: The total planned value when the project is complete

    BAC is the total authorized budget for the project, representing the sum of all planned values at completion.

  3. A project manager notices the SPI is 0.8 and CPI is 0.9. Which statement is most accurate?

    Answer: The project is behind schedule and over budget

    SPI < 1 means behind schedule; CPI < 1 means over budget — both performance indices are below 1.

  4. What is the purpose of a cost baseline in project management?

    Answer: To serve as the approved time-phased budget against which performance is measured

    The cost baseline is the approved, time-phased budget used to measure and monitor project cost performance.

  5. Rough Order of Magnitude (ROM) estimates typically carry an accuracy range of:

    Answer: -25% to +75%

    ROM estimates are typically accurate within -25% to +75% and are used in early project phases when limited information is available.

  6. When applying the three-point estimating (PERT) formula for cost, what weights are applied to optimistic (O), most likely (M), and pessimistic (P)?

    Answer: O×1, M×4, P×1 divided by 6

    The PERT formula is (O + 4M + P) / 6, giving the most weight to the most likely estimate.

  7. Which document formally authorizes the project cost baseline and is approved by stakeholders?

    Answer: Project Budget

    The approved Project Budget (which includes the cost baseline plus management reserve) is formally authorized by stakeholders.