CPD - Certified Project Director Practice Test
CPD CPD Resource Management & Team Development
What is a resource histogram used for in project management?
Select your answer
A
Mapping stakeholder influence
B
Displaying resource utilization over time to identify over-allocation or gaps
C
Calculating earned value
D
Documenting lessons learned