CPCS Theory Practice Test
CPCS Working Near Services & Site Hazards
Before excavating or operating plant near underground services, what must be done?
Select your answer
A
Obtain service drawings, use CAT scanning, and establish exclusion zones around identified services
B
Only use CAT scanning — drawings are not reliable
C
Start carefully and stop if anything is struck
D
Underground services are the main contractor's responsibility only
Hint