  1. What does CPCS stand for? Construction Plant Competence Scheme
  2. What must a plant operator do if they are unsure whether a service has been correctly identified and isolated before excavation? Stop work and contact the supervisor — do not proceed until confirmation is received
  3. Under PUWER, when must a risk assessment for plant use be reviewed? When there is reason to believe it is no longer valid or after a significant change
  4. What does LOLER require regarding the competence of the appointed person for a lifting operation? They must be competent in planning and supervising lifting operations
  5. A pre-use check reveals the machine's horn is not functioning. What should the operator do? Take the plant out of service and report the defect
  6. What is the risk of operating plant on a slope steeper than the manufacturer's specified gradient? The plant may overturn laterally or tip forward, causing serious injury or death
  7. What hazard is created when an excavator operates near overhead power lines? Risk of electrocution through arcing or direct contact
  8. Which document provides the written authority for a lifting operation to proceed, detailing the method, equipment, personnel and hazards? A lifting plan or method statement
  9. What does 'duty of care' mean for a crane operator under LOLER? The operator must take reasonable care to ensure lifting operations are carried out safely
  10. A site manager asks a plant operator to use equipment outside its rated capacity. What should the operator do? Refuse and report the request to the appropriate authority
  11. What is the primary purpose of a pre-use check on construction plant? To identify defects or hazards before operation begins
  12. Under PUWER, what must be recorded following a plant inspection? The results of the inspection and any remedial actions required
  13. Which colour CPCS card indicates a trained operator who has not yet achieved full competency? Red
  14. How often must lifting equipment that is used for lifting persons be thoroughly examined under LOLER? Every 6 months
  15. What is the function of the excavator's slew brake? It controls and stops the rotation of the upper structure
  16. Who is the 'Appointed Person' in a crane lifting operation under BS 7121? The person responsible for planning and directing the lifting operation
  17. What does a blue CPCS card indicate about the holder? They are a trained operator working towards their NVQ
  18. What should an operator do before tipping a load at a spoil heap or trench edge? Ensure stop blocks are in place and approach cautiously at a safe distance from the edge
  19. What is an exclusion zone in the context of a lifting operation? An area below and around the lift from which all non-essential personnel are excluded
  20. Which regulation specifically requires that guards are fitted to dangerous parts of construction plant? PUWER Regulation 11
  21. What colour represents electrical services (high voltage) in the UK underground colour coding? Red
  22. What does LOLER stand for? Lifting Operations and Lifting Equipment Regulations 1998
  23. What colour represents a gas pipe in UK underground service identification? Yellow
  24. What does RIDDOR require in relation to construction plant incidents? Certain serious injuries, dangerous occurrences, and fatalities must be reported
  25. What is the correct boom position when travelling a tracked excavator across site? Boom retracted with bucket low to the ground, just above surface level
  26. A plant operator is working near a communications cable (telephone/data). What colour identifies this type of service? Grey or purple
  27. What is the correct procedure for picking up a pallet of bricks with a telehandler fitted with forks? Approach slowly, insert forks fully under the load, tilt back slightly, then raise
  28. In what situation should a forward tipping dumper never be used? To transport persons in the skip or anywhere other than the operator's seat
  29. What is the correct procedure before slewing an excavator with a loaded bucket? Check the swing area is clear of personnel and obstructions
  30. What does the CPCS category A09 relate to? Excavator — 360 degrees