Which situation MOST clearly requires a contract manager to invoke the 'duty to disclose' under federal procurement rules?
-
A
A contractor completes work ahead of schedule
-
B
A contractor discovers it has been overpaid due to a billing error
-
C
A contractor requests a contract extension for convenience
-
D
A contractor hires additional staff to meet performance requirements