A contract manager is asked to backdate a contract modification to avoid a late delivery penalty. This action is BEST characterized as:
-
A
A minor administrative convenience that saves time
-
B
Falsification of official records and a serious ethical violation
-
C
Acceptable if both parties agree to the backdating
-
D
A standard practice when delays are the government's fault