A contract manager discovers that a sole-source vendor is consistently delivering late. What is the BEST first step?
-
A
Immediately terminate the contract
-
B
Issue a cure notice requesting corrective action within a defined timeframe
-
C
Reduce payment by 50% until performance improves
-
D
File a legal claim for breach of contract