A contract manager receives a unilateral change order increasing scope. The contractor must perform but should immediately:
-
A
Submit a written protest and REA within contractually specified timeframes
-
B
Stop work until a bilateral modification is signed
-
C
Accept the change without documentation to preserve the relationship
-
D
Escalate directly to the contracting officer's supervisor