What is the primary purpose of a Dispute Review Board (DRB) in large construction contracts?
-
A
To provide real-time, non-binding recommendations before disputes escalate to arbitration
-
B
To replace arbitration as a binding adjudication method
-
C
To audit contractor invoices for compliance
-
D
To oversee change order approvals