A contract manager discovers that a subcontractor has been falsifying progress reports. What is the FIRST action the contract manager should take?
-
A
Terminate the subcontract immediately without notice
-
B
Document the discrepancies and report them through the proper internal channels
-
C
Ignore the issue if the project is on schedule
-
D
Confront the subcontractor publicly at the next project meeting