Which of the following is the BEST indicator that a contract's risk management plan is effective?
-
A
No risks were identified during the planning phase
-
B
Identified risks are regularly reviewed and response plans are updated as conditions change
-
C
All risks were transferred to the contractor through fixed-price contract type
-
D
The contract was completed within the original schedule