A contracting officer is evaluating a high-value IT services contract. Which risk mitigation tool provides the MOST comprehensive protection against contractor non-performance?
-
A
A liquidated damages clause alone
-
B
A combination of performance bond, liquidated damages, and robust monitoring provisions
-
C
An indemnification clause covering all eventualities
-
D
A firm-fixed-price contract structure