When a contractor submits a request for equitable adjustment (REA), what must it demonstrate?
Select your answer
A
Proof of fraudulent government intent
B
That the government caused a change entitling the contractor to additional compensation
C
That the contractor's costs exceeded the contract ceiling
D
That the contracting officer failed to issue a cure notice
Hint