CPCM Exam Practice Test
CPCM Contract Closeout and Termination 3
The novation agreement process is required when:
Select your answer
A
A contractor changes its legal name without a change of ownership
B
A contractor transfers its government contracts to a successor in interest due to a merger or acquisition
C
A subcontractor takes over performance from the prime contractor
D
The contracting officer is replaced during contract performance
Hint