An owner issues a unilateral change order without the contractor's agreement on price. Under most standard construction contracts, the contractor must:
-
A
Refuse to perform until the price is negotiated and agreed upon
-
B
Perform the work and preserve its right to additional compensation through the claims process
-
C
Perform the work only if the owner provides a written price commitment within 7 days
-
D
Seek injunctive relief to prevent the owner from issuing unilateral orders