The Spearin Doctrine holds that when an owner provides design specifications, the owner implicitly warrants that:
-
A
The contractor will complete work within budget
-
B
Following the specifications will produce a satisfactory result
-
C
The architect has reviewed all shop drawings
-
D
The contractor bears all risk of design errors