In Earned Value Management (EVM), what does the Schedule Performance Index (SPI) measure?
-
A
The ratio of actual cost to planned value
-
B
The ratio of earned value to planned value
-
C
The ratio of earned value to actual cost
-
D
The ratio of budget at completion to estimate at completion