What is the primary function of a 'contingency fund' in a construction project budget?
-
A
To cover the contractor's expected profit
-
B
To provide a financial reserve for unforeseen costs within the defined project scope
-
C
To fund changes in project scope requested by the owner
-
D
To reimburse the designer for additional services