What is the primary purpose of a 'Schedule of Values' submitted by a general contractor at project start?
-
A
Establish the owner's budget
-
B
Allocate the contract sum across project components as the basis for progress payment applications
-
C
Define the subcontractor bid amounts
-
D
List material delivery schedules