โ† All CPC Flashcard Decks

Project Budget & Cost Control Flashcards

6 cards from real CPC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 Project Budget & Cost Control flashcards as text
  1. What is the cost baseline in project management?

    Answer: The approved time-phased budget used to measure and monitor project cost performance

    The cost baseline is the approved, time-phased budget that serves as the reference point for earned value analysis.

  2. Analogous estimating uses:

    Answer: Historical data from similar past projects to estimate cost or duration

    Analogous estimating is a top-down technique that leverages actual results from similar previous projects.

  3. Which cost estimate type has the widest accuracy range and is produced earliest in the project?

    Answer: Rough order of magnitude (ROM)

    A ROM estimate is produced with minimal information and typically carries an accuracy range of -25% to +75%.

  4. Management reserve differs from contingency reserve in that:

    Answer: Management reserve covers unknown unknowns, while contingency reserve covers known risks

    Contingency reserve addresses identified risks; management reserve handles unforeseen issues that fall outside the risk register.

  5. A project has spent $50,000 but was supposed to spend $40,000 by this point. This means the project is:

    Answer: Over budget (cost overrun)

    Spending more than planned at a given point signals a cost overrun that must be investigated and addressed.

  6. Parametric estimating calculates cost or duration by:

    Answer: Multiplying a unit cost or rate by a measurable quantity

    Parametric estimating uses a statistical relationship between project parameters (e.g., cost per square foot) to produce estimates.