A project manager notices that the team is consistently missing sprint goals due to scope additions mid-sprint. Which practice best addresses this?
-
A
Allow scope changes if the client approves them
-
B
Protect the sprint backlog from changes once the sprint begins
-
C
Add buffer time to each sprint to absorb new requests
-
D
Reassign tasks dynamically based on incoming requests