Which feature most clearly distinguishes a PPP from traditional public procurement?
-
A
The private partner is paid in a single lump sum on completion
-
B
Significant risk and management responsibility are transferred to the private partner over a long-term contract
-
C
The government owns no assets at any stage
-
D
Design is always completed by the public sector before tender