In an availability-payment PPP, what is the primary consequence when an asset is deemed 'unavailable' under the contract definitions?
-
A
The procuring authority assumes operation of the asset
-
B
The contract is automatically terminated
-
C
A deduction is applied to the unitary payment
-
D
The private partner must pay liquidated damages to users