Core Concepts and Principles Flashcards
7 cards from real CP3P practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Core Concepts and Principles flashcards as text
In a DBFOM contract, what does the 'F' signify?
Answer: Finance
DBFOM stands for Design-Build-Finance-Operate-Maintain, with the private partner raising project finance.
Which contract type transfers the least lifecycle responsibility to the private sector?
Answer: Design-Build (DB)
Design-Build covers only design and construction, leaving finance, operation, and maintenance with the public sector.
Under a Build-Own-Operate (BOO) arrangement, what typically happens to the asset at the end of the contract?
Answer: The private partner retains ownership
In BOO, the private party owns the asset indefinitely and there is usually no transfer obligation, unlike BOT.
Payment deductions in an availability-based PPP are primarily designed to:
Answer: Incentivize performance by reducing payments when availability or service standards are not met
Deductions link payment to performance, giving the private partner a financial incentive to meet service standards.
What is 'optimism bias' in PPP appraisal?
Answer: The tendency to underestimate project costs and durations, often adjusted for in the PSC
Optimism bias is the systematic tendency to underestimate costs and timelines; appraisals apply uplifts to correct it.
Which risk is usually best retained by the public sector?
Answer: Changes in law that specifically target the project or PPP sector
Discriminatory change in law is within government control, so the public sector typically retains it.
A 'handback' provision in a PPP contract ensures that:
Answer: The asset is returned to the public sector in a specified condition at contract expiry
Handback requirements set the condition the asset must be in at expiry, often backed by inspections and retention funds.