← All CP3P Flashcard Decks

Communication and Documentation Flashcards

7 cards from real CP3P practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Communication and Documentation flashcards as text
  1. After contract signature, many PPP frameworks recommend proactive disclosure of which information?

    Answer: The contract and key terms, with commercially sensitive data redacted

    Good practice, such as the World Bank disclosure framework, calls for publishing the contract and key information while protecting genuinely confidential data.

  2. What document is used by the contracting authority to guide day-to-day oversight of a PPP during the operations phase?

    Answer: Contract Management Manual

    The Contract Management Manual describes roles, procedures, monitoring, and reporting obligations for managing the contract.

  3. Which document is generally used to prequalify bidders by assessing their technical and financial capacity?

    Answer: Request for Qualifications (RFQ)

    The RFQ invites interested parties to demonstrate capability so a shortlist can be formed.

  4. A private partner must submit periodic reports on availability and service quality. What is the primary purpose of these reports?

    Answer: To support performance monitoring and payment deductions where applicable

    Performance reports feed the payment mechanism and allow the authority to verify compliance with output specifications.

  5. Which practice best protects the integrity of communications between bidders and the procuring authority during the tender?

    Answer: Designating a single point of contact and a formal communication channel

    A single designated channel prevents improper influence and ensures all exchanges are recorded.

  6. What should a procuring authority do when it must change the RFP after it has been issued?

    Answer: Issue a formal addendum to all bidders and consider extending the deadline

    Formal addenda distributed to all bidders, with adequate time to respond, preserve fairness.

  7. Which document records the reasons the evaluation committee selected the preferred bidder?

    Answer: Evaluation Report

    The Evaluation Report documents scoring and justification, supporting approvals and any challenge.