What is the 'preferred bidder' stage in a P3 procurement process?
-
A
The first stage of issuing a request for proposals
-
B
The stage where one bidder is selected for exclusive contract negotiation after evaluation of final bids
-
C
The public announcement of project cancellation
-
D
The point when construction begins