COR Federal Acquisition Regulations 3 — Questions and Answers
Question 1: Under FAR Subpart 4.7, what is the required retention period for contract files after final payment?
- 3 years
- 6 years and 3 months (Correct answer)
- 10 years
- Indefinitely
Correct answer: 6 years and 3 months
FAR 4.703 generally requires retention of contractor records for 6 years and 3 months after final payment for most contracts.
Question 2: The Anti-Deficiency Act prohibits federal agencies from doing which of the following?
- Using multiple award contracts
- Obligating funds in excess of appropriations (Correct answer)
- Awarding contracts to small businesses
- Conducting sole-source acquisitions
Correct answer: Obligating funds in excess of appropriations
The Anti-Deficiency Act prohibits agencies from obligating or expending funds beyond what has been appropriated by Congress.
Question 3: Which FAR clause gives the government the right to terminate a contract for its convenience?
- FAR 52.249-1 (Correct answer)
- FAR 52.233-1
- FAR 52.243-1
- FAR 52.222-1
Correct answer: FAR 52.249-1
FAR 52.249-1 (and related clauses in FAR 52.249 series) provides the government's right to terminate for convenience.
Question 4: A COR is reviewing a contractor's invoice. Under the Prompt Payment Act, when must the government pay a proper invoice?
- Within 15 days
- Within 30 days (Correct answer)
- Within 45 days
- Within 60 days
Correct answer: Within 30 days
The Prompt Payment Act requires the government to pay proper invoices within 30 days or pay interest penalties.
Question 5: Which of the following best describes an 'undefinitized contract action' (UCA)?
- A contract awarded without competition
- A contract where work begins before final price is agreed upon (Correct answer)
- A contract with no scope of work defined
- A contract that has been terminated for convenience
Correct answer: A contract where work begins before final price is agreed upon
A UCA (also called a letter contract) allows work to begin while price and other terms are still being negotiated.
Question 6: Under FAR Part 9, which type of debarment action requires the contractor to be given notice and opportunity to respond?
- Proposed debarment
- Suspension
- Both proposed debarment and suspension (Correct answer)
- Neither, as both are administrative actions
Correct answer: Both proposed debarment and suspension
FAR 9.406 and 9.407 both require that the contractor receive notice and an opportunity to respond to proposed debarment and suspension.
Question 7: A contractor requests a change to the contract delivery schedule citing excusable delay. Under FAR 52.249-14, which of the following qualifies as an excusable delay?
- Subcontractor financial difficulties
- Acts of God or natural disasters (Correct answer)
- Labor cost overruns
- Poor project management
Correct answer: Acts of God or natural disasters
FAR 52.249-14 identifies excusable delays as those beyond the contractor's control, such as acts of God, acts of government, fires, floods, and epidemics.
Under FAR Subpart 4.7, what is the required retention period for contract files after final payment?