โ† All Construction Management Flashcard Decks

Contract Administration & Procurement Flashcards

6 cards from real Construction Management practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 Contract Administration & Procurement flashcards as text
  1. Which document sets the standard general terms and conditions that govern the relationship between contractor, owner, and architect on most US commercial projects?

    Answer: AIA A201

    AIA A201 General Conditions of the Contract for Construction is the most widely used standard document defining roles, rights, and responsibilities of the three primary parties.

  2. In a construction dispute, what is the role of a Dispute Review Board (DRB)?

    Answer: To hear disputes in real time and issue non-binding recommendations before litigation

    A DRB is a standing panel of neutral experts who periodically visit the project and provide recommendations on disputes, helping parties avoid costly litigation.

  3. What is the primary purpose of requiring contractors to submit a Schedule of Values?

    Answer: To allocate the contract price across work items for progress payment applications

    A Schedule of Values breaks the contract sum into line items so the owner and architect can verify the value of completed work when reviewing monthly pay applications.

  4. Front-loading a Schedule of Values means the contractor:

    Answer: Assigns higher values to early work items to improve early cash flow

    Front-loading assigns disproportionately high values to early work items so the contractor receives more cash early, which owners and architects look for and question.

  5. A liquidated damages clause in a construction contract specifies:

    Answer: A predetermined dollar amount the contractor owes per day of delay beyond the completion date

    Liquidated damages are a pre-agreed daily dollar amount compensating the owner for losses caused by contractor delay, which must represent a reasonable estimate of actual harm.

  6. A 'no damages for delay' clause in a construction contract generally means:

    Answer: The contractor can only seek a time extension, not additional money, for owner-caused delays

    No-damages-for-delay clauses restrict the contractor's remedy for most owner-caused delays to a time extension only, though courts in many states limit their enforceability.