Construction Management Cost Estimating & Financial Management 2 — Questions and Answers
Question 1: Earned Value Management (EVM) calculates Schedule Performance Index (SPI) as:
- Earned Value ÷ Planned Value (EV/PV) (Correct answer)
- Actual Cost ÷ Earned Value (AC/EV)
- Earned Value ÷ Actual Cost (EV/AC)
- Planned Value ÷ Budget at Completion (PV/BAC)
Correct answer: Earned Value ÷ Planned Value (EV/PV)
SPI = EV/PV; a value below 1.0 indicates the project is behind schedule relative to the planned baseline.
Question 2: In Earned Value Management, a Cost Performance Index (CPI) of 0.85 means:
- For every $1 spent, only $0.85 of budgeted work is accomplished (Correct answer)
- The project is 15% ahead of schedule
- The project will finish 15% under budget
- The contractor earns $0.85 profit per dollar billed
Correct answer: For every $1 spent, only $0.85 of budgeted work is accomplished
CPI = EV/AC; a CPI of 0.85 signals the project is over budget — $1.18 is being spent for every $1.00 of budgeted work completed.
Question 3: A construction project's contingency budget is best described as:
- A reserve for identified and unidentified risks within the project scope (Correct answer)
- Profit set aside after project completion
- The owner's allowance for scope additions
- Overhead costs for the home office
Correct answer: A reserve for identified and unidentified risks within the project scope
Contingency is a planned reserve within the project budget to cover cost growth from known risks and unforeseen scope uncertainties, not for profit or scope changes.
Question 4: The term 'cost-to-complete' (CTC) in project financial management refers to:
- The estimated cost needed to finish the remaining work (Correct answer)
- Total costs spent to date on the project
- The original budget minus contingency
- A contractor's final invoice to the owner
Correct answer: The estimated cost needed to finish the remaining work
Cost-to-complete is a forward-looking forecast of expenses required to finish all remaining project activities, used to update the Estimate at Completion (EAC).
Question 5: Which document does a contractor typically submit monthly to request payment for completed work?
- Application for payment (pay application) (Correct answer)
- Certified payroll report
- Contractor's daily log
- Notice of completion
Correct answer: Application for payment (pay application)
A monthly application for payment, referencing the Schedule of Values, is the standard mechanism for contractors to formally request compensation for work completed.
Question 6: Break-even analysis in construction helps a contractor determine:
- The minimum revenue required to cover all fixed and variable costs (Correct answer)
- The optimal crew size for maximum productivity
- The safest markup percentage for competitive bidding
- The point at which retainage is released
Correct answer: The minimum revenue required to cover all fixed and variable costs
Break-even analysis identifies the volume of work or revenue at which total costs equal total income, with no profit or loss, guiding pricing and capacity decisions.
Earned Value Management (EVM) calculates Schedule Performance Index (SPI) as: