Work Management and Planning Flashcards

6 cards from real CMRP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Work Management and Planning flashcards as text
  1. What is job kitting in maintenance planning?

    Answer: Assembling all parts, materials, tools, and documents for a job into one package before work begins

    Job kitting pre-assembles everything required for a planned job, eliminating travel time and delays.

  2. What is the purpose of shutdown and turnaround planning?

    Answer: To plan concentrated maintenance during a planned equipment outage ensuring maximum work in minimum downtime

    Shutdown planning coordinates all maintenance, inspection, and capital work during a planned outage.

  3. What is the difference between planned and scheduled maintenance?

    Answer: Planned has been scoped and resourced; scheduled has been assigned specific dates for execution

    Planning determines what resources are needed; scheduling determines when the job will be performed.

  4. What is the purpose of work order coding for failure analysis?

    Answer: To systematically categorize failure modes, causes, and actions for pattern analysis

    Standardized coding enables analysis of failure patterns, identification of chronic problems, and data-driven optimization.

  5. What is emergency work management?

    Answer: Establishing a systematic process for urgent unplanned needs while minimizing disruption to planned schedules

    Emergency work management provides a structured approach to handling urgent unplanned maintenance.

  6. What is post-maintenance testing and inspection?

    Answer: Verifying maintenance was completed correctly and equipment functions properly before return to service

    Post-maintenance testing verifies repairs are complete, equipment meets specifications, and safety devices function before returning to production.