A municipality receives only one responsive bid on a formal solicitation. The procurement officer should MOST likely:
-
A
Award the contract to the sole bidder immediately
-
B
Cancel and re-bid with revised specifications or broader outreach
-
C
Negotiate price directly with the sole bidder without further process
-
D
Waive the competitive requirement and sole-source the contract