A building permit application is incomplete when submitted. Under most municipal codes, the permit clock (review period) typically begins:
-
A
On the date the incomplete application is first received
-
B
Only after the applicant submits all required documents and the application is deemed complete
-
C
After a mandatory 10-day waiting period
-
D
When the applicant pays the permit fee