A Qualified Products List (QPL) is PRIMARILY used to:
Answer: Pre-approve products that have met testing requirements before solicitation
A QPL identifies products pre-tested and approved as meeting specifications, streamlining procurement by eliminating per-purchase testing.
Which document establishes the legal authority, duties, and limitations of a procurement officer in a municipality?
Answer: The purchasing ordinance or procurement code
A municipal purchasing ordinance or procurement code defines the procurement officer's legal authority, thresholds, and responsibilities.
When a contract requires the contractor to obtain a performance bond, the bond PRIMARILY protects the municipality against:
Answer: The contractor's failure to complete the work as specified
A performance bond guarantees that a surety will complete the project or compensate the owner if the contractor defaults on performance obligations.
The term 'piggybacking' in public procurement refers to:
Answer: Using another government entity's competitively awarded contract
Piggybacking allows a municipality to purchase under another public agency's competitively solicited contract, satisfying competition requirements without conducting its own bid.
A 'materially unbalanced bid' is MOST problematic because it:
Answer: Front-loads high prices on early items to accelerate cash flow at the owner's expense
A materially unbalanced bid artificially inflates early-work unit prices and deflates later items, imposing excess costs on the municipality regardless of final quantities.
Which of the following BEST describes 'reverse auction' procurement?
Answer: Vendors compete by lowering their prices in real time until the lowest price wins
In a reverse auction, sellers compete by reducing their prices in real time, driving the purchase price down; it is the opposite of a traditional auction.
A municipality wishes to award a multi-year service contract. The MAIN budget risk it must address is:
Answer: The lack of annual appropriation authority beyond the current fiscal year
Most municipal governments cannot legally obligate funds beyond the current fiscal year without specific legislative authority, making multi-year contracts contingent on future appropriations.