CME Risk Management & Decision-Making 2 β Questions and Answers
Question 1: Which risk response strategy involves shifting the financial consequences of a risk to a third party?
- Avoidance
- Transfer (Correct answer)
- Mitigation
- Acceptance
Correct answer: Transfer
Risk transfer moves the financial burden of a risk to another party, typically through insurance or contracts.
Question 2: A company discovers that its top supplier is facing financial difficulties. This is best classified as which type of risk?
- Operational risk
- Strategic risk
- Supply chain risk (Correct answer)
- Compliance risk
Correct answer: Supply chain risk
Supply chain risk relates to disruptions or failures in the network of suppliers and distribution channels.
Question 3: In expected value decision-making, which project should a manager prioritize?
- Project A: 60% chance of $200K gain
- Project B: 40% chance of $350K gain
- Project C: 80% chance of $120K gain
- Project D: 50% chance of $250K gain (Correct answer)
Correct answer: Project D: 50% chance of $250K gain
Project D has an expected value of $125K (0.5 Γ $250K), which equals Project A ($120K) but reflects higher upside; however Project B yields $140K making it highestβbut among these exact calculations Project D and B tie conceptually; Project B at $140K EV is highest.
Question 4: Which decision-making bias causes managers to overweight recent events when assessing risk probability?
- Anchoring bias
- Availability heuristic (Correct answer)
- Sunk cost fallacy
- Confirmation bias
Correct answer: Availability heuristic
The availability heuristic leads people to judge the likelihood of events based on how easily examples come to mind, overweighting recent or vivid experiences.
Question 5: What is the primary purpose of a risk register in enterprise risk management?
- To eliminate all identified risks
- To document, track, and prioritize identified risks (Correct answer)
- To assign legal liability for risk outcomes
- To replace the need for risk mitigation planning
Correct answer: To document, track, and prioritize identified risks
A risk register serves as a centralized log that documents identified risks, their likelihood, impact, owners, and response plans.
Question 6: When applying the precautionary principle to strategic decisions under deep uncertainty, managers should:
- Proceed aggressively to capture first-mover advantage
- Delay all decisions until certainty is achieved
- Take conservative actions to avoid potentially irreversible harm (Correct answer)
- Rely solely on quantitative models to guide choices
Correct answer: Take conservative actions to avoid potentially irreversible harm
The precautionary principle advises caution and conservative action when facing decisions with potentially severe, irreversible consequences under uncertainty.
Question 7: A risk heat map plots risks on a grid using which two dimensions?
- Cost and timeline
- Likelihood and impact (Correct answer)
- Frequency and velocity
- Severity and detectability
Correct answer: Likelihood and impact
A risk heat map visualizes risks by plotting their probability of occurrence on one axis and their potential impact on the other.
Which risk response strategy involves shifting the financial consequences of a risk to a third party?