A municipality experiences repeated cost overruns on capital projects. Which project management practice would MOST directly address systematic underestimation of project costs during planning?
-
A
Increasing contractor liquidated damages penalties
-
B
Implementing reference class forecasting using historical data from similar projects
-
C
Requiring additional insurance bonds from contractors
-
D
Shortening the design phase to reduce consultant fees