Project Management & Public Works Planning Flashcards
7 cards from real CME practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Management & Public Works Planning flashcards as text
A municipal engineer is using Earned Value Management (EVM) on a road resurfacing project. The Schedule Performance Index (SPI) is 0.85. What does this indicate?
Answer: The project is progressing at 85% of the planned rate
An SPI of 0.85 means the project is earning only $0.85 of planned value for every $1.00 of scheduled work, indicating it is behind schedule.
Which project delivery method transfers the most design and construction risk to the private sector?
Answer: Public-Private Partnership (P3)
P3 arrangements transfer the broadest range of risks—including design, construction, financing, and operations—to the private partner.
A capital improvement plan (CIP) for a municipality typically covers what time horizon?
Answer: 5 to 10 years
Most municipal CIPs span 5 to 10 years to align infrastructure investment with budget forecasting and long-range planning cycles.
During public works project planning, a Level of Service (LOS) standard is primarily used to:
Answer: Establish performance benchmarks for infrastructure
LOS standards define the minimum acceptable performance thresholds for infrastructure systems such as roads, water, and wastewater.
What is the primary purpose of a constructability review during project design?
Answer: To identify design elements that may cause construction difficulty or cost overruns
Constructability reviews identify design features that are difficult or costly to build, allowing corrections before construction documents are finalized.
A municipal stormwater infrastructure project is funded by a State Revolving Fund (SRF) loan. Which federal requirement is most likely triggered?
Answer: Davis-Bacon Act prevailing wage requirements
SRF loans are federally capitalized, triggering Davis-Bacon Act requirements that mandate prevailing wage rates for construction workers.
In a Critical Path Method (CPM) schedule, 'float' or 'slack' refers to:
Answer: The amount of time an activity can be delayed without delaying project completion
Float is the amount of time a non-critical activity can slip without affecting the overall project completion date.