Grounding, Bonding & Overcurrent Protection Flashcards
7 cards from real CME practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Grounding, Bonding & Overcurrent Protection flashcards as text
Per NEC 240.4(D), what is the maximum overcurrent protection permitted for a 12 AWG copper branch-circuit conductor?
Answer: 20A
NEC 240.4(D)(5) limits overcurrent protection for 12 AWG copper conductors to a maximum of 20A.
What is the minimum burial depth for a ground ring below the surface of the earth per NEC 250.52(A)(4)?
Answer: 30 inches
NEC 250.52(A)(4) requires a ground ring to be installed at least 2½ feet (30 inches) below the surface of the earth.
When conductors are installed in parallel in multiple raceways, how must equipment grounding conductors be installed per NEC 250.122(F)?
Answer: In each raceway, each sized per Table 250.122 based on the overcurrent device
NEC 250.122(F) requires an EGC to be installed in each raceway when parallel conductors are used, with each EGC sized per Table 250.122 for the circuit overcurrent device.
A concrete-encased electrode (Ufer ground) must contain at least how many feet of bare copper conductor or steel rebar per NEC 250.52(A)(3)?
Answer: 20 feet
NEC 250.52(A)(3) requires at least 20 feet of bare copper conductor (4 AWG or larger) or 20 feet of steel rebar (½ inch or larger) encased in concrete for a concrete-encased electrode.
What is the primary function of the equipment grounding conductor (EGC) in a branch circuit?
Answer: To provide a low-impedance fault current path that enables overcurrent device operation
The EGC provides a low-impedance path for fault current to return to the source, ensuring sufficient current flows to operate the overcurrent protective device and clear the fault.
Per NEC 230.95, ground-fault protection of equipment (GFPE) is required for solidly grounded wye services exceeding 150V to ground but not exceeding 600V phase-to-phase when the service disconnect is rated at or above:
Answer: 1000A
NEC 230.95 requires GFPE for solidly grounded wye services with service disconnecting means rated 1000A or more to protect against high-level arcing ground faults.
A supply-side bonding jumper is used to bond metal enclosures on which side of the service or separately derived system?
Answer: The supply side, between the service or separately derived system source and the first disconnecting means
Per NEC 250.102(C), supply-side bonding jumpers bond metal enclosures and raceways on the supply side of the service or between a separately derived system and its first disconnecting means.