A project is experiencing scope creep that threatens the schedule. Which project management technique helps control this most effectively?
-
A
Compressing the schedule by fast-tracking
-
B
Implementing a formal change control process
-
C
Adding staff to absorb additional scope
-
D
Reducing quality standards to meet the deadline