In lean project planning, what does a 'pull planning' session primarily accomplish?
-
A
Assigns tasks top-down from management
-
B
Engages the team to work backward from milestones to identify handoffs
-
C
Creates a push schedule based on resource availability
-
D
Documents risks and issues for the project register