A hospital's EHR implementation is behind schedule due to unexpected interface build complexity. Which project management response is MOST appropriate?
-
A
Extend the go-live date without stakeholder notification
-
B
Conduct a formal schedule compression analysis using fast-tracking or crashing
-
C
Remove scope items without change control approval
-
D
Reassign all interface tasks to the project manager